News from site..

Purlins... Sheathing...

9/30/2015

0 Comments

 
Picture
All floor joists fitted over living room, cantilevering through south gable. First purlins raised and spruce ply sheathing beginning - this'll give the structure it's rigidity.
0 Comments

South gable up!

9/23/2015

0 Comments

 
Happy with todays progress if mentally and physically bruised!
Picture
Living room floor joists going into position to support south gable
Picture
Making the most of the lift - my newest favourite tool, heading back to the hire firm tomorrow...
Picture
South gable wall frames lifted into place and secured with ropes and blocks - getting a feel for the final volume. Four more floor joists to fit - omitted for now to get the big lifting done.
0 Comments

All trussed up!

9/22/2015

0 Comments

 
So excited about todays work that the pun just had to happen, and some bigger photos. Very relieved to have the two big trusses now secured in place with temporary diagonal bracing until the purlins and plywood are installed to give the required structural integrity. The hand-cranked forklift proved up to the job and everything appears to be the right size. South gable wall panels to fit tomorrow, before the lift goes back to the hire company - boo!
Picture
First truss installed, supported by the lift and the edge beams whilst bracing fixed
Picture
Second truss is manoeuvred into place, gently gently!
Picture
Taking form... more bracing added
Picture
Clamp-tastic, awaiting checking with measure and spirit level before finally screwing frames together.
0 Comments

First floor framing...

9/20/2015

2 Comments

 
In preparation for the trusses we set about lifting the north gable panels into place, using the Genie lift that we're planning to use to get all the big stuff up.
North gable all up by the end of sunday, spot the flaw with the blocks supporting the purlins.
2 Comments

Trusses...

9/20/2015

0 Comments

 
When time is short updating the blog is always a bit tricky, so looking back over the last couple of weeks the focus has been on building the two large trusses that break the length of the build into manageable spans. The timber sizes got beefed up by the structural engineer, so principal elements are made from great big 225x100mm timber, bolted with 3mm steel plate and M16 bolts. I estimate the finished trusses are between 275-300kg each, so lifting them into place on top of the edge beams is the next big challenge!
0 Comments

    Author

    Mike Hawkins is a co-op member and is responsible for the design and management of the build. He'll also live in it when its finished - hooray! He teaches future architects at Leicester DeMontfort and Birmingham City universities.

    Archives

    November 2017
    June 2016
    April 2016
    March 2016
    February 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015

    Categories

    All

    RSS Feed

Powered by Create your own unique website with customizable templates.
  • Home
  • What's a Housing Co-op?
    • Wild Peak Housing Co-op
  • The Build
    • Blog
    • Design
    • Volunteering
  • Links
  • Contact