This site is under construction
  • Home
  • What's a Housing Co-op?
    • Wild Peak Housing Co-op
  • The Build
    • Blog
    • Design
    • Volunteering
  • Links
  • Contact

News from site..

Shower cap

10/20/2015

0 Comments

 
So having realised that the fragmented nature of work on the build means that roofing isn't going to happen in one go, and accepting the likely onset of bad weather before long, I decided to put a temporary roof of d.p.m. (damp proof membrane) and roofing lath over the structure. This can be rolled up to work on the roof, but means that the inside space is now relatively dry and timber can be kept in better conditions without spending a long time each day uncovering/ recovering materials. Although the d.p.m. is much tougher than the polyethene used to cover the walls, it will still be vulnerable in high winds so I'm looking to get the roof on asap. External wall insulation work continues, as well as prepping for the installation of windows and doors.
0 Comments

More purlins, more ply, keeping the rain off?!

10/11/2015

0 Comments

 
A great weekend, thankfully dry, spent with lovely members of the former Nautia housing co-op who came along to lend a hand. Floor joists were fitted at the north end allowing us to lay out sheets of ply to form a safe working platform at either end. The remaining purlins were raised into place and secured - almost at the end of the big-section timber jobs. So really satisfying and definitely getting a feel for the spaces. Now the big question is one of prioritisation in terms of weather proofing - whether to consolidate what we've done so far, or to crack on with the roof. I want to avoid the ply getting wet, especially on the outside where moisture could get trapped by the foil faced insulation that'll go on next...
0 Comments

Purlins... Sheathing...

9/30/2015

0 Comments

 
Picture
All floor joists fitted over living room, cantilevering through south gable. First purlins raised and spruce ply sheathing beginning - this'll give the structure it's rigidity.
0 Comments

South gable up!

9/23/2015

0 Comments

 
Happy with todays progress if mentally and physically bruised!
Picture
Living room floor joists going into position to support south gable
Picture
Making the most of the lift - my newest favourite tool, heading back to the hire firm tomorrow...
Picture
South gable wall frames lifted into place and secured with ropes and blocks - getting a feel for the final volume. Four more floor joists to fit - omitted for now to get the big lifting done.
0 Comments

All trussed up!

9/22/2015

0 Comments

 
So excited about todays work that the pun just had to happen, and some bigger photos. Very relieved to have the two big trusses now secured in place with temporary diagonal bracing until the purlins and plywood are installed to give the required structural integrity. The hand-cranked forklift proved up to the job and everything appears to be the right size. South gable wall panels to fit tomorrow, before the lift goes back to the hire company - boo!
Picture
First truss installed, supported by the lift and the edge beams whilst bracing fixed
Picture
Second truss is manoeuvred into place, gently gently!
Picture
Taking form... more bracing added
Picture
Clamp-tastic, awaiting checking with measure and spirit level before finally screwing frames together.
0 Comments

First floor framing...

9/20/2015

2 Comments

 
In preparation for the trusses we set about lifting the north gable panels into place, using the Genie lift that we're planning to use to get all the big stuff up.
North gable all up by the end of sunday, spot the flaw with the blocks supporting the purlins.
2 Comments

Trusses...

9/20/2015

0 Comments

 
When time is short updating the blog is always a bit tricky, so looking back over the last couple of weeks the focus has been on building the two large trusses that break the length of the build into manageable spans. The timber sizes got beefed up by the structural engineer, so principal elements are made from great big 225x100mm timber, bolted with 3mm steel plate and M16 bolts. I estimate the finished trusses are between 275-300kg each, so lifting them into place on top of the edge beams is the next big challenge!
0 Comments

Back to site...

8/25/2015

0 Comments

 
After a week in Wales and various other things going on we're back to the build. A bolted softwood edge beam avoids the complexity of lots of lintels and provides a consistent bearing for the upper wall panels. North elevation has no openings so no beam there. Younger family members were put to work!
Picture
A neglected labour force! Bolting the edge beams together before raising.
Picture
Steel plates cut and painted, ready for bolting the main trusses together. Trusses will be made of large section timber, around 1/4 tonne each - currently investigating how best to lift them into place. Vintage pillar drill is apparently ex. Rolls Royce.
Picture
Edge beams in position, temporarily clamped to allow for 'tweaking'.
Picture
NE corner, first floor frame installed. Edge beam 'steps' to allow high level square window in kitchen.
Picture
NW corner, first floor frame in place.
0 Comments

More timber framing...

8/4/2015

0 Comments

 
All timber frame panels now fabricated & laid flat on the slab, protected from the elements.
0 Comments

Timber frame started...

7/23/2015

1 Comment

 
Excited to make a start on the timber frame panels. Thanks to a Wild Peak work weekend we had 2 great volunteers who spent the day cutting 100x50 (4x2") C24 graded timber to a variety of lengths with the fantastic new chop saw. These were then pinned together with 90mm nails fired in by a borrowed nail gun - fast work. Sash clamps useful for holding frames in place while nailing, diagonals checked repeatedly to ensure squareness. By the end of the day we had frames for the west and north elevation complete up to the level of the edge beam. Although it would have been very satisfying to put them up they'd be vulnerable to warping in the sun and rain, so covered in tarpaulin until the rest are completed... Once up they'll be sheathed in 18mm plywood to keep the structure rigid, then insulation, a breather membrane and external cladding..... before winter sets in!
1 Comment
<<Previous
Forward>>

    Author

    Mike Hawkins is a co-op member and is responsible for the design and management of the build. He'll also live in it when its finished - hooray! He teaches future architects at Leicester DeMontfort and Birmingham City universities.

    Archives

    November 2017
    June 2016
    April 2016
    March 2016
    February 2016
    December 2015
    November 2015
    October 2015
    September 2015
    August 2015
    July 2015

    Categories

    All

    RSS Feed

Powered by Create your own unique website with customizable templates.
  • Home
  • What's a Housing Co-op?
    • Wild Peak Housing Co-op
  • The Build
    • Blog
    • Design
    • Volunteering
  • Links
  • Contact